AEC Project No.: 1825
Environmental Premit : EP-516/2016
Port Shelter Phase 3, Po Toi O Sewage Treatment Plant EM&A                                                                     
Air and Noise Quality Baseline Monitoring Schedule
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec
        *Noise *Noise *Noise
  ** 1 - hr TSP  ** 1 - hr TSP  ** 1 - hr TSP 
  **24- hr TSP **24- hr TSP **24- hr TSP
27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 1-Jan 2-Jan
*Noise *Noise *Noise *Noise *Noise *Noise *Noise
** 1 - hr TSP  ** 1 - hr TSP  ** 1 - hr TSP  ** 1 - hr TSP  ** 1 - hr TSP  ** 1 - hr TSP  ** 1 - hr TSP 
**24- hr TSP **24- hr TSP **24- hr TSP **24- hr TSP **24- hr TSP **24- hr TSP **24- hr TSP
3-Jan 4-Jan 5-Jan 6-Jan 7-Jan 8-Jan 9-Jan
*Noise            
** 1 - hr TSP 
**24- hr TSP
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
             
         
         
* Noise Monitoring Locations: NSM1N,NMS2N,NMS3Namd NMS4N
** 1hr TSP and 24- hr TSP Monitoring Locations:  ASM1N ,ASM2N1, ASN3N and ASM4N