Environmental Premit No.: EP-516/2016
Port Shelter Phase 3, Po Toi O Sewage Treatment Plant EM&A                                                                     
2021/03 Air and Noise Quality Impact Monitoring Schedule
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
28-Feb 1-Mar 2-Mar 3-Mar 4-Mar 5-Mar 6-Mar
      *Noise      
  ** 1 - hr TSP 
  **24- hr TSP
7-Mar 8-Mar 9-Mar 10-Mar 11-Mar 12-Mar 13-Mar
    *Noise        
  ** 1 - hr TSP 
  **24- hr TSP
14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar
  *Noise          
  ** 1 - hr TSP  ** 1 - hr TSP 
  **24- hr TSP **24- hr TSP
21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar
        *Noise    
  ** 1 - hr TSP 
  **24- hr TSP
28-Mar 29-Mar 30-Mar 31-Mar 1-Apr 2-Apr 3-Apr
  *Noise          
  ** 1 - hr TSP       
  **24- hr TSP      
4-Apr 5-Apr 6-Apr 7-Apr 8-Apr 9-Apr 10-Apr
             
         
         
* Noise Monitoring Locations: NSM1N,NMS2N,NMS3Namd NMS4N
** 1hr TSP and 24- hr TSP Monitoring Locations:  ASM1N ,ASM2N1, ASN3N and ASM4N