AEC Project No.: 1825
Environmental Premit : EP-516/2016
Port Shelter Phase 3, Po Toi O Sewage Treatment Plant EM&A                                                                     
Water Quality Baseline Monitoring Schedule
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec
        * Water Quality Baseline Monitoring   * Water Quality Baseline Monitoring
     
     
20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec
    * Water Quality Baseline Monitoring   * Water Quality Baseline Monitoring   * Water Quality Baseline Monitoring
         
         
27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 1-Jan 2-Jan
    * Water Quality Baseline Monitoring   * Water Quality Baseline Monitoring   * Water Quality Baseline Monitoring
         
         
3-Jan 4-Jan 5-Jan 6-Jan 7-Jan 8-Jan 9-Jan
    * Water Quality Baseline Monitoring   * Water Quality Baseline Monitoring   * Water Quality Baseline Monitoring
       
       
10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan
    * Water Quality Baseline Monitoring        
         
         
17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan
             
         
         
Remarks
1. Water sampling will be conducted +/- 1 hour of the predicted tides time.
2. Predicted tides time were reference from Hong Kong Observatory (Tai Miu Wan Station).