Environmental Premit No. EP-516/2016
Port Shelter Phase 3, Po Toi O Sewage Treatment Plant EM&A                                                                     
2021/05 Air and Noise Quality Impact Monitoring Schedule
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 1-May
        Monitoirng Suspended   Monitoirng Suspended
 
 
2-May 3-May 4-May 5-May 6-May 7-May 8-May
  Monitoirng Suspended Monitoirng Suspended Monitoirng Suspended Monitoirng Suspended Monitoirng Suspended Monitoirng Suspended
 
 
9-May 10-May 11-May 12-May 13-May 14-May 15-May
  Monitoirng Suspended Monitoirng Suspended Monitoirng Suspended Monitoirng Suspended Monitoirng Suspended Monitoirng Suspended
 
 
16-May 17-May 18-May 19-May 20-May 21-May 22-May
  Monitoirng Suspended Monitoirng Suspended Monitoirng Suspended Monitoirng Suspended Monitoirng Suspended Monitoirng Suspended
 
 
23-May 24-May 25-May 26-May 27-May 28-May 29-May
  Monitoirng Suspended Monitoirng Suspended Monitoirng Suspended Monitoirng Suspended Monitoirng Suspended Monitoirng Suspended
 
 
30-May 31-May 1-Jun 2-Jun 3-Jun 4-Jun 5-Jun
  Monitoirng Suspended          
       
       
* Noise Monitoring Locations: NSM1N,NMS2N,NMS3Namd NMS4N
** 1hr TSP and 24- hr TSP Monitoring Locations:  ASM1N ,ASM2N1, ASN3N and ASM4N
#Commencement Date of construction works revised to 10 May 2021, no construction works conduct until 10 May 2021.The monitoring was suspended.